MAJOR PROJECTS
RESUME
TOLKO HIGH PRAIRIE OSB MILL
Electrical installation for Tolko’s rebuild of the Forming, Press and Finishing lines that were damaged during a fire. Work consists of all new trays, cabling, MCC gear and equipment, 4160v distribution equipment, and new 25KV feeders
Location
High Prairie, AB
Approx. contract value
PROJECT DURATION
12 Months
ELEMENTAL ENERGY EAST STRATHMORE SOLAR 17MW
Electrical AC and DC works and AESO feeder/Substation construction.
Location
Strathmore, AB
Approx. contract value
PROJECT DURATION
16 Months
CAPITAL POWER STRATHMORE 50MW
Electrical AC and DC works and AESO feeder/Substation construction
Location
Strathmore, AB
Approx. contract value
PROJECT DURATION
8 Months
ENBRIDGE TAYLOR CS-01 SEGREGATION PROJECT
Segregation of sweet assets from the sour assets between Enbridge and North River Midstream. Addition of new MCC, Switchgear Building, Meter Bldg, Compressor, Shop and Office/Control Room location.
Location
Taylor, BC
Approx. contract value
PROJECT DURATION
11 Months
ENBRIDGE CHETWYND/WILLOW FLATS CS-02 PROJECT
Addition of a new solar compressor to the existing facility, new MCC, Generator Bldg, Switchgear Bldg, Analyzer, Fuel Gas Skid, Cooler area and multiple new valve stations within the facility.
Location
Chetwynd, BC
Approx. contract value
PROJECT DURATION
9 Months
BLACK SWAN c-46-C PHASE IIa PLANT EXPANSION
Plant expansion including MCC additions, 6 new compressor buildings piped and wired on site, and multiple other process buildings. Water Hub segment and pipeline tie-in upgrades.
Location
Fort St. John, BC
Approx. contract value
PROJECT DURATION
2 Months
NUVISTA PIPESTONE NORTH GAS PLANT
Grassroots facility. New MCC, 2 Inlet Separators, 4 sales gas compressors, 2 Dehy's,VRU Compressor, Recycle Compressor, HP & LP Flare systems, Generator package, Fuel Gas Conditioning, Instrument Air Package, 8 storage tanks, Office, shop and control room.
Location
Grande Prairie, AB
Approx. contract value
PROJECT DURATION
6 Months
ADVANTAGE WEMBLEY 03-11 FACILITY
Complete New Facility, Inlet Seperation, Sales Compression, Satibilizer Feed, Amine Sweetening, Process Refrigeration, VRU, Propane Refrigeration, Acid Gas Injection, Recyle Compressors, On-site Generation, Heat Medium, VRU, I/A, Fuel Gas, Lube Oil utilities.
Location
Grande Prairie, AB
Approx. contract value
PROJECT DURATION
7 Months
CSV KARR EXPANSION
Gas plant expansion to 150MMSCFD, 5kv, 480v MCCs, 2 turbine generators, 2 main compressors, gas chilling train, 2 overhead compressors, gas sweetening unit, heat medium, high-pressure and low-pressure flare, LACT, sour mix compressor, NGL truck-outs, booster pumps, sales metering building, tank farm, HCL truck-outs, and incinerator.
Location
Grande Prairie, AB
Approx. contract value
PROJECT DURATION
8 Months
PEMBINA KAKWA PHASE VI PUMP STATION
Addition of MCC building (480VAC/5KV), Switchgear, MCC, UPS, 2000HP VFD's, 2- 2000HP Shipping Pump Skid.
Location
Grande Prairie, AB
Approx. contract value
Project duration
5 Months
STORM RESOURCES NIG CREEK
New sour gas plant, 50 MMSCFD, with inlet separation, sales compression, stabilizer feed, amine sweetening, process refrigeration, VRU, propane refrigeration, acid gas injection, recycle compressors, on-site generation, heat medium, VRU, I/A, fuel gas, and lube oil utilities.
Location
Fort St. John, BC
Approx. contract value
PROJECT DURATION
3 Months
SEMCAMS KARR BATTERY
Oil battery, 480v MCC & generation, with inlet separator, oil treater, sales compression, recycle compression, dehydration, water storage, oil storage, slop tank, sales gas metering, VRU, oil LACT, waterinjection well, instrument air, and fuel gas package.
Location
Grande Prairie, AB
Approx. contract value
PROJECT DURATION
4 Months
SEVEN GENERATIONS 5 WELL PAD
5 new wells, Wet meter skids, sand separators, HP flare, FKOD, Generator, MCC/PLC, Fuel gas scrubber, I/A skid.
Location
Grande Prairie, AB
Approx. contract value
PROJECT DURATION
1 Month
VALHALLA 13-21 GAS PLANT EXPANSION
Existing facility expansion with a new MCC building and new electrical service. Addition of new amine sweetening package, condensate stabilizer package, refrigeration package, C4+ storage bullet. We also produced a new water storage tank, condensate storage tanks, heat medium package, acid gas compressor, and lube oil coalescer.
Location
Grande Prairie, AB
Approx. contract value
PROJECT DURATION
3 Months
SEVEN GENERATIONS ENERGY 10-16 SUPERPAD EXPANSION
Existing facility expansion with new MCC, inlet separator, 2 sales gas compressors, GSU, 2 Dehy's, water transfer pump, VRU compressor, storage bullet & building, high-pressure and low-pressure flare systems, skin-tight generator package, fuel gas conditioning, instrument air package, and storage tanks, as well as an office and control room.
Location
Grande Prairie, AB
Approx. contract value
PROJECT DURATION
6 Months
NUVISTA ENERGY PIPESTONE COMPRESSOR STATION
Grassroots facility with new MCC, 2 inlet separators, 4 sales gas compressors, 2 Dehy's, VRU compressor, recycle compressor, high-pressure and low-pressure flare systems, generator package, fuel gas conditioning, instrument air package, and 8 storage tanks, as well as an office, shop and control room.
Location
Grande Prairie, AB
Approx. contract value
PROJECT DURATION
5 Months
TOURMALINE GUNDY DEEP CUT GAS PLANT
198MMSCFD Grassroots facility. New 480v MCC and triple 5kV power generation with inlet separators and sales gas compressors. The project also included VRU/ Sales gas splitter area, heat medium, mol sieve/cryogenic area, stabilizer/air cooler area, tank farm, bullets, trucking load/unload, and LACT area, as well as a control room, office, and shop/garage area.
Location
Fort St. John, BC
Approx. contract value
PROJECT DURATION
5 Months
HAMMERHEAD RESOURCES 11-12 GOLD CREEK OIL BATTERY
Grassroots facility with new MCC, 2 inlet separators, 3 sales gas compressors, 2 H2S scavenger skids, 2 Dehy's, 2 treater skids, de-sand transfer Pump, VRU Compressor, recycle compressor, high-pressure and low-pressure flare systems, generator package, fuel gas conditioning, incinerator, LACT, and 8 storage tanks, as well as an office and control room.
Location
Grande Prairie, AB
Approx. contract value
PROJECT DURATION
4 Months
PEMBINA LATOR PHASE V EXPANSION
New 4160v MCC building with standby 3 new mainline pumps, 1 booster pump, and a new trap and sump tank.
Location
Grande Prairie, AB
Approx. contract value
PROJECT DURATION
5 Months
CDN Controls is a fully-integrated, people-focused, one-stop-shop for Instrumentation & Electrical services in Western Canada. Our fully-integrated model means we are capable of tackling any project, and we guarantee we will meet or exceed your expectations. Leading the industry since 2011, we also specialize in automation, communication, measurement, meter proving, combustion and emissions services, and more. Functioning on a commitment to high-quality work, outstanding customer service, and unparalleled reliability, it’s no question CDN Controls is a leader in Instrumentation & Electrical throughout Western Canada.